The first contract, for $667,125, was to Henley Roofing Co. for roof upgrades to Bonny Kate and Sequoyah elementary schools.
Comments are the sole responsibility of the person posting them. You agree not to post comments that are off topic, dematory, obscene,Online Higher Education.legal advice online. abusive, threatening or an invasion of privacy. Violators may be banned. Click here for our full user agreement.
In other board business, Education Information members also approved on first reading revisions to its policy on selecting its student representative.
The Pond Gap project, a $365,000 contract plus reimbursable expenses to The Lewis Group Architects, includes the addition of 16 classrooms, a new kitchen/cafeteria area, a gymnasium, two new music classrooms, an art room, an expansion of administrative office space and a new front entry complete with a secure vestibule.
........
During the school boards work session on Monday night, schools Superintendent Jim McIntyre said the proposed changes came out of discussion with board members.
The districts first student representative who doesnt vote, but provides student input and perspective served during the 2008-09 school year. Abdalla Husain, a senior at South-Doyle High School, is the boards current student representative.
with the recent cronyism in the security contracts, the school board needs additional scrutiny..
The contract also calls for renovating the school for its community schools initiative. For that piece, some spaces will be changed to accommodate adult classrooms, meeting rooms and a community clinic.
KNS Says:
With a school of Archetecture, at UT why pay unneeded thousands upon thousands, to cronys, to draw plans, just more good ol boys, in the pipeline..
The board will vote on a second reading of the policy at its March meeting.
Join the local community School Matters, where you can discuss local schools and education.
Board member Pam Trainor said the panel will begin taking applications for the position soon.
The other two contracts went to architecture firms to design additions and renovations at Pond Gap and Shannondale elementaries.
The last contract approved by the board was for $215,000 to McCarty, Holsaple, McCarty Inc. for additions and renovations at Shannondale Elementary.
Among the proposed revisions was to include the outgoing student representative as part of the group that can be chosen for the selection committee to choose the next years representative and to have the boards chair designate the five-person committee in February.
Knox County school board members on Wednesday night approved three contracts for improvements at several elementary schools.
The project includes the design of 14 to 16 new classrooms and the expansions of the schools cafeteria and media center.
The project also includes renovating two restrooms, designing a teachers work area and transforming an existing classroom space into a special-education suite.
The other two contracts went to architecture firms to design additions and renovations anight school for high school Knox school board approves contracts for additions renovationst Pond Gap and Shannondale elementaries.
These firms are crony loaded, some exboard member packed, and charge as much for plans, as the construction.. Architecture graduates can be hired for near minimum wage, 12-15$ an hour, now, due to current lack of demand in the job market..